Electricity bill guide
Contract Demand: the number you pay for, used or not.
Your Contract Demand puts a floor under your fixed charges every month, and a ceiling your demand must not cross. Set it too high and you pay for capacity you never use; set it too low and you pay in penalties. Here is how to find the right number.
What Contract Demand is
Contract Demand (CD) is the load, in kVA or kW, sanctioned in your supply agreement with the DISCOM — the capacity it keeps ready for you. Maximum Demand (MD) is what you actually draw: the highest 15- or 30-minute average in the billing month.
Contract Demand shapes your bill in two ways. It sets a minimum for your fixed charges, and it is the line above which excess-demand charges start. Getting it wrong costs money in both directions.
Too high: paying for capacity you never use
Many tariffs bill the fixed (demand) charge on the higher of your actual MD or a percentage of Contract Demand. In Uttar Pradesh, for example, it is the higher of MD or 75% of Contract Demand. If your MD stays below that floor, you pay for demand you never drew, every month.
Take an illustrative plant that took 600 kVA of Contract Demand years ago, for an expansion that never came. Its highest MD in the last 12 months was 430 kVA, and its MD averages 395 kVA a month. The demand rate is ₹300 per kVA a month.
| Illustrative plant | CD 600 kVA | CD 455 kVA |
|---|---|---|
| Billing floor (75% of CD) | 450 kVA | 341.25 kVA |
| Average monthly MD | 395 kVA | 395 kVA |
| Demand billed each month | 450 kVA | 395 kVA |
| Fixed charge per month | ₹1,35,000 | ₹1,18,500 |
| Fixed charge per year | ₹16,20,000 | ₹14,22,000 |
Illustrative figures. Demand rates, the billing floor and the demand unit differ by state, DISCOM and consumer category — check your tariff order and bill.
That is ₹1,98,000 a year for capacity the plant never drew. A Contract Demand of 455 kVA still leaves about 5% headroom above the year’s highest MD.
Too low: excess demand and forced revisions
Set Contract Demand too close to your real peaks and MD will cross it. Every kVA above Contract Demand attracts an excess-demand charge, in many tariffs at twice the normal demand rate. The MD penalty guide works through an example.
Repeated crossings carry a second cost. Many supply codes let the DISCOM raise your Contract Demand after repeated excess months. Gujarat’s Supply Code, for example, lets the DISCOM enhance Contract Demand if MD exceeds it by 5% or more at least four times in a financial year. The higher Contract Demand then raises your fixed charges every month after.
A reduction or an increase is an application to your DISCOM. Rules differ on how often Contract Demand can be changed, how long a change takes and any charges involved. Check your DISCOM’s procedure before you apply, and apply with your MD history in hand.
How to choose the right Contract Demand
- Start from 12 months of MD, not one bill. Seasonal loads, such as summer cooling or a winter process, can set the year’s peak in one or two months.
- Add some headroom. About 5% above the year’s highest MD leaves room for normal variation without paying for idle capacity.
- Count only growth that is actually planned: a new line, a new building, a large machine on order.
- Fix avoidable peaks first. If one restart after a power cut set the year’s MD, staggering starts may let you contract less.
- On a kVA tariff, fix power factor first. Every point of power factor lowers kVA demand for the same kW.
How KONDUKTOR® EMS helps
KONDUKTOR® EMS reads the multifunction meters already on your panels and tracks demand against the Contract Demand you set for each meter.
- Running MD shows against Contract Demand live, and your team is warned as it approaches.
- Month-by-month MD history turns amber and then red as MD nears Contract Demand.
- A Contract Demand optimizer reads 12 months of MD and suggests a Contract Demand with headroom, with the yearly saving in rupees — or confirms yours is already right-sized.
- It records when each meter peaked, so you know which panel set the month’s MD.
Common questions
What is the difference between Contract Demand and Maximum Demand?+
Contract Demand is the capacity sanctioned in your supply agreement, the most you agreed to draw. Maximum Demand is what you actually drew: the highest 15- or 30-minute average in the billing month. Fixed charges are usually based on one or both, and MD above Contract Demand attracts an excess-demand charge.
Can we reduce our Contract Demand?+
Usually, yes, by applying to your DISCOM. Each DISCOM has its own rules on how often Contract Demand can be changed and how long a change takes, so check the procedure first. Twelve months of MD history is the evidence you need for the new figure.
How much headroom should we keep above our highest MD?+
A common starting point is about 5% above the highest MD of the last 12 months, plus any load growth that is actually planned. More headroom costs fixed charges every month; less risks excess-demand charges.
Is Contract Demand the same as connected load?+
No. Connected load is the total rating of everything installed. Contract Demand is the demand you contract with the DISCOM, and it is usually well below connected load, because machines rarely all run at full load together.
Size your Contract Demand from your own data.